12 C1572M (9/05)
System Setup
This section provides information about the following:
•
Overview of tasks necessary to set up a 9760 system
•
Unpacking the CM9700-CC1 controller and CM9760-MXB matrix bay
•
Installing the CM9700-CC1 controller
•
Installing CM9760-MXB matrix bay(s)
•
Verifying system operation
SYSTEM SETUP OVERVIEW
The following provides an overview of the tasks necessary to set up a 9760 system and prepare the system for operation. It is recommended that
you perform the tasks in the order listed below.
NOTE:
For detailed instructions to perform the tasks listed below for setup of the CM9700-CC1 and CM9760-MXB, refer to the
Unpacking,
Installing the CM9700-CC1 Controller,
and
Installing CM9760-MXB Matrix Bay(s)
sections in this manual. For detailed instructions to perform the
tasks listed below for setup of all other devices in your system, refer to the manual provided for the device.
1. Unpack all equipment. Verify delivery according to the packing slip. Keep all manuals and cables with the associated equipment.
2. Select a location within a standard 19-inch (48.26 cm) EIA rack for each device to be mounted.
3. Mount each device into the selected location within a rack.
4. Verify that the correct number of cards and power supplies have been installed in each CM9760-MXB in the system according to the system
order.
5. Install the CM9700-MGR software on a PC, and then do the following:
a. Copy the startconfig.psm file from the CM9700 Factory Configuration Data CD.
b. Open the startconfig.psm file using the CM9700-MGR.
6. Connect all system devices to the CM9700-CC1 according to the CM9700-CC1 port assignments listed in the System 9760 port assignment
table.
7. Connect power cabling to all devices.
8. Power on all devices connected to the CM9700-CC1.
9. Power on the CM9700-CC1.
10. Check diagnostic LEDs on devices to ensure that the devices are operating properly.
11. Connect all other cabling—for example, video input and output cabling—to all devices as appropriate.
12. Verify system operation (refer to the
Verifying System Operation
section in this manual).
DANGER:
When mounting equipment into a rack, always install equipment starting from the bottom of the rack. Installing equipment
starting from the top of the rack can cause the rack to topple.
NOTES:
•
The CM9700-MGR software is contained on the CM9700 Resource CD, which is provided in the System 9760 binder. For CM9700-MGR
software installation instructions, refer to the CM9700-MGR Software Guide, which is also provided in the System 9760 binder.
•
The CM9700 Factory Configuration Data CD is provided in the System 9760 binder.
•
Do not modify the system using the CM9700-MGR until after you have verified system operation in step 12 below.
NOTE:
The System 9760 port assignment table, titled “System 9760 Factory Default Port Settings,” is provided in the System 9760 binder.
Detailed information about the System 9760 port assignment table is provided in the
Installing the CM9700-CC1 Controller
section in this
manual.