The following is a quick preview of the steps required for first time installations. Each item is discussed in detail later in this section.
Determine clearance, ventilation and service access requirements.
Determine checkout counter layout taking into account package flow, cable routing and power requirements.
Choose the mounting option which provides the best cable/power access and unit stability.
Unpack the unit and remove the shipping hardware from the scale arms.
Make the appropriate countertop cutouts and install all support brackets.
Place the unit in the counter.
Install the platter.
Follow the steps under the correct interface to connect the cables and power supply.
Configure the unit for the correct interface.
Calibrate the scale.
SITE REQUIREMENTS
Before installing the StratosH scanner, please consider the following items.
Vertical Clearance
A minimum clearance height of 7.00" from the checkout counter surface is needed for the vertical 'hood' on all of the scanner models.
Ventilation and Spacing
All StratosH models have a die-cast housing to dissipate heat allowing the unit to operate without a ventilation fan. Honeywell
recommends that the temperature surrounding the unit does not exceed 40°C (104°F). There should be adequate convection and
minimal heat producing equipment in close proximity of the unit. A cooling fan with a filter is recommended if there will be a conveyor
motor or other heat producing equipment close to the unit that will create a high temperature environment.
Adequate spacing between the unit and the checkout counter opening is required for proper operation of the scale. When the
scanner/scale model is mounted properly, the scale platter should be able to move up and down freely without hitting the edges of the
checkout counter cutout. Refer to Installing the Unit in the Counter for detailed cutout dimensions and mounting instructions.
Service Access
When routing and installing the cable(s) and power supply, make sure to leave access so that these components may be swapped
easily without the need to remove the unit from the checkout counter.
When changing the StratosSWAP optics engine modules, Honeywell recommends removing the unit completely from the checkout
counter.
When calibrating or zeroing the scale, do not remove the unit from the checkout counter. Refer to the Scale Operation Section of this
guide for detailed instructions on zeroing and calibration.