Lucent Technologies Release 6 Security Camera User Manual


 
DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets
555-230-112
Issue 5
May 1998
Install Management Terminal and Activate System
Page 3-7Activate the System
3
Set Up Management Terminal
Each management terminal requires a different setup procedure. Refer to the
installation and usage instructions packed with the management terminal.
Install Management Applications
The PC-based Management Applications are installed according to the complete
installation instructions provided in
Management Applications Operations
,
585-229-202.
Activate the System
Instructions are provided to activate Release 6 and later systems. To activate a
G3V4 and earlier system, refer to
DEFINITY Communications System Generic 3
Installation and Test
, 555-230-104.
NOTE:
To prevent unnecessary trouble tickets, do not enable the system alarms
(Alarm Origination feature) until all installation and administration
procedures are completed.
!
CAUTION:
It may be necessary to reseat circuit packs. To prevent damage from static
electricity, always wear an Electromagnetic Compatibility (EMC) wrist strap
(comcode 900698226) when handling all system components.
Install Translation Card (Release 6si in MCC
Cabinet)
If a Release 6r system is installed, skip this section.
1. Insert the translation card into the TN777B Network Control circuit pack in
the direction indicated by the arrow on the label.
Power Up the System
AC-Powered System
1. Set the circuit breakers on the AC power panel to ON. If the system is high
or critical reliability, power-up the EPN cabinet first, then the PPN cabinet.
Always
power up the PPN cabinet
last
.
2. Set the cabinet circuit breakers to ON. This starts the system initialization
and test. All red LEDs on the circuit packs go on and then off.
3. Skip to ‘‘
Verify Messages on Terminal’’.