DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets
555-230-112
Issue 5
May 1998
Cable Ductwork
Page C-2
C
Equipment room layout and expected growth determines which method to use.
Installation of an overhead rack is covered by
Cable Racks
(800-614-157).
NOTE
:
Install all screws in all appropriate places to comply with electromagnetic
interference (EMI) requirements for shielding.
Figure C-1. Typical Layout of Assembled Ductwork
Figure Notes
1. I/O Cross-Isle Trough
2. Shielded Intercabinet Duct
3. AC Power Cable Duct
4. Front of Cabinets
5. I/O Ducts to Cross-Connect Field
duct1KLC 071796