Lucent Technologies Release 6 Security Camera User Manual


 
DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets
555-230-112
Issue 5
May 1998
Cable Ductwork
Page C-7
C
Install Intercabinet Shielded Ducts
1. Loosen (do not remove) the four bolts holding the dust cover to the cable
access hole in the top of the cabinet.
Figure C-3. Dust Cover Removal
2. Remove the dust cover by sliding it in the direction shown by the arrow in
Figure C-3
. Move the dust cover until it clears the bolts.
3. Set the cabinet riser (“A” in Figure C-4
) with its base in place of the dust
cover just removed. The four slots in its base should be just behind the
bolts and the heads of the two middle bolts should have cleared the holes
provided for them. Push the riser forward to seat the bolts in the four slots
in the base of the riser. Then tighten the bolts.
plate KLC 071696