Lucent Technologies Release 6 Security Camera User Manual


 
DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets
555-230-112
Issue 5
May 1998
Test Telephones and Other Equipment
Page 6-5Test Basic Rate Interface
6
Local Test
1. Log in and enter the test inads-link command.
2. Request remote access personnel to verify a trouble ticket was created.
3. Check error log to verify no problems.
4. Log off the system.
Test Basic Rate Interface
Check for normal voice telephone function (dial tone, ability to make and receive
calls). Check for the correct Service Profile Identifier (SPID) on a display
telephone and the management terminal.
Test Duplication Option Processing
Element Interchange
The process of the standby Processing Element (PE) taking over for the active PE
is referred to as a PE Interchange. This interchange should not be performed
immediately after powering up the system. Wait a few minutes to allow the system
to complete its internal tests. The system default is PE_B after powering up the
system, so the active PE should be the B processor for this test, and the
interchange should make PE_A the active PE. Verify the system can successfully
perform a PE interchange.
1. At the management terminal, verify the screen displays PE_B in the upper
right corner.
2. Enter check status command. Verify PE_B is in the standby mode. If it is,
proceed to Step 4. If it is not, proceed to Step 3.
3. Enter refresh-spr-standby command.
4. Enter reset system interchange command. The management terminal
will be logged off and a beep will be heard.
5. Login and verify that the screen displays PE_A in the upper right corner.
NOTE:
Processor A’s yellow light is on and its green LED is off. Processor
B’s yellow and green LEDs are off. The system is alarm free.
6. Make system test call. The call must complete and the conversation must
be satisfactory.